Approximately 10 years ago, the City of Tallahassee, with input from citizens and business owners, developed the outline for a destination district in the heart of Tallahassee, a connection between the two universities close to downtown that would be the hub of arts and culture in Tallahassee. With this vision in mind, the City adopted the Gaines Street Revitalization Plan. The goal was to create a pedestrian friendly street and improve infrastructure to help develop a destination district that would be home to a blend of commercial, residential and cultural uses.

The funds to pay for the majority of this project come from sales tax, not property taxes. Voters initially approved the funding for the Gaines Street project as part of the Blueprint 2000 sales tax extension. Subsequently, in 2004, the City of Tallahassee and Leon County agreed to set aside $27.7 million of Blueprint 2000 discretionary funds to pay for the road construction, property acquisition and development incentives. Additionally, the City received another $7 million in road maintenance funds from the State of Florida when the road right-of-way was transferred in 2008.

As part of the plan, electric lines would be moved off the street, deteriorating underground utility lines would be replaced, and the road would be rebuilt within the existing right-of-way to a 2-way, 2-lane street with limited on-street parking.

The project began in earnest in 2009, with the replacement of underground utilities along the corridor. Around this time, electric lines and poles were moved, where possible, from the Gaines Street right-of-way to mid-block locations.

In May 2010, Public Works began construction on the reconfiguration of the road. Work took place between Monroe and Macomb streets and was completed in early fall 2011.

The City put out the bid for Phase II, which runs from Macomb Street to near Stone Valley Way, in early summer 2011. Bids were open in July. Bids came back higher than estimated and had to undergo an extensive review by staff. The contract for Phase II was awarded to Allen's Excavation Inc. in October by the City Commission with a 4-0 vote.